ISLAMABAD, February 5: Service Road (West) being part of under construction Koral Interchange has been opened for traffic. The commuters heading to Airport from Rawat can use Service Road (West).
While construction work on Service Road (East) of Koral Interchange and 64 meter long roof of central flyover consists of 64 graders has also been completed. The flyover has been facilitated with three lanes on its both sides as well as footpaths for pedestrian.
These details were stated during a briefing to the Mayor of Islamabad and Chairman Capital Development Authority (CDA), Sheikh Anser Aziz on the eve of his visit to Koral Interchange.
On this occasion, Member Engineering, CDA, Asad Mehboob Kiyani and Project Director Koral Interchange were also present.
Reviewing progress about the development activities at Koral Interchange, Mayor of Islamabad and Chairman CDA, Sheikh Anser Aziz said that delay in completion of Koral Interchange project would not be tolerated.
He has directed for an effective strategy to complete construction work on different parts of the Koral Interchange simultaneously within stipulated time.
He said that Islamabad Expressway Signal Free Corridor project is of immense importance. He further said that after completion of Koral Interchange, work on different phases of Islamabad Expressway Signal Free Corridor project would also be started in line with the directions of Prime Minister of Pakistan, Mian Muhammad Nawaz Sharif.
Mayor of Islamabad and Chairman CDA, Sheikh Anser Aziz directed the Project Director to start immediate landscaping work on loops, which has less traffic flow on it. He further directed for submission of different suggestions for water sprinkling system for landscaping at the loops of Koral Interchange.
Mayor of Islamabad and Chairman CDA, Sheikh Anser Aziz expressed his annoyance for non-installation electric light poles and directed the concerned formations for installation of light poles of same specification. – PR